Capital Projects Status

The following is a summary list of active Capital Improvement Projects within the city limits of Hoover.  As individual projects progress, their status will be updated.  As projects are completed, they will be removed from the list. 

ALL PROJECTS AS OF OCTOBER 30, 2023

Project Type Lead Agency Status Current Status (% 
​Complete)
Next Milestone Next Milestone (Target Date)

ROADWAYS

         
Valleydale Rd Widening (Little) - Widens Valleydale Rd from Riverchase Pkwy to Business Center Drive
ALDOT ROW Acquisition 30% Bid Process 2024
Valleydale Rd Widening (Big) - Widens Valleydale Rd to five lanes from Caldwell Mill Rd to Hwy 280. ALDOT ROW Acquisition
​94 Total tracts
​3 Pending​
95% Utility Coordination   2023
South Shades Crest Rd, Additional Northbound Lane - Adds a northbound lane on South Shades Crest Road from Willow Lakes Drive to Hwy 150.                Jefferson County      Preliminary Design 90% Construction Summer 2024
Galleria Blvd Extension - County led project that extends Galleria Blvd by Chick-Fil-A to Old Montgomery Highway Jefferson County Right of Way Acquisition 80% Construction 2023
Exit 9 Interchange City of Hoover/
ALDOT
Preliminary Design 40% Bid Process 2025

SIDEWALKS,GREENWAYS & TRAILS

         
Chapel Rd Sidewalks - Extend sidewalk from Matzek Drive to Park Ave.  (See more info.) ALDOT Construction
​ 
85% Completion Winter 2023
US Hwy 150 Sidewalk - Provides sidewalk on one side of Hwy 150 from Hwy 31 to Cahaba River Estates. ALDOT Design & Planning  90% Right of Way  Acquisition TBD
Alford Avenue Sidewalks - Phase 1 - Constructs sidewalks along Alford Avenue from Haden Street to Pine Lane and Haden Street from Alford Avenue to Blue Ridge Blvd. City of Hoover Final Design Stages 95% Right of Way Acquisition TBD
Old Columbiana Road Sidewalks - Patton Chapel Road to Green Valley Elementary City of Hoover Construction 5% Completion Spring 2024
Al Seier Road Sidewalks - East of Sulphur Springs Road to Ball Park City of Hoover Design Stage 95% Bid Process Winter 2024
Sulphur Springs Road Sidewalks - Preserve Parkway to Al Seier Road City of Hoover Design Stage 95% Bid Process Winter 2024

GENERAL / MISC

.
         
Gwin/Simmons Traffic Signal Installation City of Hoover Construction 90% Completion Fall 2023
Hwy 31 at Hendrick/Hoover Commons Traffic Signal Upgrades City of Hoover Construction 10% Completion Winter 2023
Hwy 150 at ATI Pkwy Traffic Signal Installation City of Hoover Permitting 50% Construction Fall 2023
Hwy 31 at Patton Chapel North Traffic Signal Upgrades City of Hoover Construction 5% Completion Spring 2024
Upgrade Woodford Pump Station City of Hoover Construction 15% Completion Spring 2024
Applecross Pump Station Replacement City of Hoover Construction 60% Completion Spring 2024
Maiden Lane - Replace double 36" CMP with 36 ft. of double 36" RCP and replace two headwalls City of Hoover Construction 5% Completion Winter 2023
Pickleball Courts @ Veterans Park City of Hoover Construction 30% Completion Summer 2024
Lake Forest Dam Rehabilitation City of Hoover Construction 50% Completion Fall 2025
Hoover Met Parking Lot City of Hoover Construction 10% Completion Spring 2024