Capital Improvement Projects

The following is a summary list of active Capital Improvement Projects within the city limits of Hoover.  As individual projects progress, their status will be updated.  As projects are completed, they will be removed from the list. 


ALL PROJECTS AS OF June 25, 2020

Project Type Lead Agency Status Current Status (% 
​Complete)
Next Milestone Next Milestone (Target Date)

ROADWAYS

         
Patton Chapel Road Improvement - Modifies two existing intersections into one, in front of Gwin Elementary School. Extends sidewalk along Patton Chapel Rd.  For additional information on this project, contact Jefferson County Roads
​and Transportation at (205) 325-5141. (See More Info.)
Jefferson County Construction   Completion of    Bridge
08/20
Valleydale Rd/Highway 261 Widening - Widens Valleydale Rd/Hwy 261 from Riverchase Pkwy to Bearden Rd. (collaborative effort with Shelby County)
ALDOT Design 70% ROW Acquisition Summer 2020
Valleydale Rd Widening (Big) - Widens Valleydale Rd to five lanes from Caldwell Mill Rd to Hwy 280. ALDOT ROW Acquisition
​94 Total tracts
​7 Pending​
85% Utility Relocation       2021
South Shades Crest Rd, Additional Northbound Lane - Adds a northbound lane on South Shades Crest Road from Willow Lakes drive to Hwy 150.                Jefferson County      Permitting Process 70% Construction TBD - Coordinating efforts with Jefferson County & CSX Railroad

SIDEWALKS, GREENWAYS & TRAILS

         
Chapel Rd Sidewalks - Extend sidewalk from Matzek Drive to Park Ave.  (See more info.) ALDOT ROW Acquisition
​30 Total tracts
​1 Pending 
97% Utility Relocation Fall of 2020
US Hwy 150 Sidewalk - Provides sidewalk on one side of Hwy 150 from Hwy 31 to Cahaba River Estates. ALDOT Design & Planning  35% ROW Acquisition TBD
Bluff Park Sidewalks - Constructs sidewalks on multiple streets in Bluff Park. (See More Info.)
ALDOT Construction 65% Completion Fall of 2020
Inverness Community Greenway - Constructs sidewalk and trail along Inverness Parkway from Valleydale Rd, through the City's Inverness Nature Park. (Awaiting environmental review) ALDOT Environmental Impact Updates
100% Bid Process Summer 2020

PARKS & FACILITIES

         
Police Training Facility - Constructs new police training facility on Municipal Drive next to Fire Station 4. City of Hoover Construction 70% Completion Summer 2020
City Hall 3rd Floor Renovations - Renovate 3rd floor city hall administrative offices and Council Chambers. City of Hoover Construction 70% Completion 08/20
Star Lake Improvement - Upgrades Star Lake Park by creating one-way traffic around the lake, widening and replacing the existing sidewalk and improving parking. (See More Info.)
City of Hoover Value Engineering      

GENERAL / MISC

.
         
US Hwy 31 Street Light Replacement, Phase 2 - Installs new street lighting along Hwy 31 from Patton Chapel Rd to I-65. ALDOT Design

95% Construction
 2021
Traffic Signal Addition - Stadium Trace Pkwy @ Flemming Pkwy City of Hoover Equipment Procurement   100% Construction      08/20
Inverness WWTP Filter Rehab
​ Repairs Existing Filters
City of Hoover Procurement 100% Construction 07/20